SR 9A - US1 to I-295
Better Jacksonville Plan, BJP-2
Status Report is for April 11, 2008
DESCRIPTION:
Provide SR 9A improvements that assist FDOT in completing connection
from I-295 to US1.
STATUS:
Current Activity: JTA transferred $4.2 million
to FDOT to construct the interchange.
Funding: Program allocation is $4.2 million.
Schedule: Project has been completed.
DBE/MBE
DBE participation will conform with FDOT policies.
SIGNIFICANT ISSUES:
None at this time.
PROJECT MANAGER: Florida Department of Transportation
(FDOT)
CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com