SR 9B - SR 9A to US 1
Better Jacksonville Plan, BJP-2
Status Report is for April 11, 2008

DESCRIPTION:
Provide a new multi-laned limited access roadway link between
SR-9A and US-1 near Bayard.
STATUS:
Current Activity: DESIGN PHASE: FDOT has completed
60% design. Final design plans are being developed.
Funding: FDOT has $124,900,000 programmed for
construction in Fiscal Year 2011/2012. Additional funding to
complete the construction is anticipated in Fiscal Year 2013/2014.
Schedule: FDOT schedule.
DBE/MBE
DBE participation will conform with FDOT policies.
SIGNIFICANT ISSUES:
The constrution is funded in year 2011/2012
PROJECT MANAGER: Florida Department of Transportation
(FDOT)
CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com