SR9B - US1 to I-95
Better Jacksonville Plan, BJP-2
Status Report is for April 11, 2008

DESCRIPTION:
Provide the necessary roadway between US1 and I-95 to complete
the link for SR 9B.
STATUS:
Current Activity: DESIGN PHASE: FDOT is at
60% design. Final design plans being developed.
Funding: FDOT has 100% of the funding for final
design and right-of-way acquisition. Although the BJP-SPP Program
allocates $15 million to this project, funding is not available
to support that allocation. FDOT does not have funding for construction.
Schedule: FDOT schedule.
DBE/MBE
DBE participation will conform with FDOT policies.
SIGNIFICANT ISSUES:
Project includes a bridge on Phillips Highway and a railroad
crossing. Total project funding is not programmed.
PROJECT MANAGER: Florida Department of Transportation
(FDOT)
CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com