Beach Boulevard Intracoastal Waterway Bridge

Better Jacksonville Plan, BJP-2
Status Report is for April 11, 2008

This is a rendered view of Beach Boulevard/Intracoastal Waterway Bridge. For more information call 630-3181.

DESCRIPTION:
Widen Beach Boulevard from four lanes to six lanes between San Pablo Road and Penman Road, including the replacement of two existing two-lane draw bridges with two fixed high level bridges with three lanes each. View rendering

STATUS:
Current Activity:
CONSTRUCTION PHASE: Construction is 57% complete. Relocation of existing utilities and construction of storm drainage continues. The new westbound bridge is now opened to two lanes of traffic in each direction. Demolition of the old lift bridge and roadway are underway. View bridge construction photo.

Funding: Revised BJP program allocation of $78.5 million, with another $436,749 from FDOT.

Schedule: The new northern bridgerecently opened. Total project construction is scheduled to be completed in the third quarter of 2009. View aerial construction map of project.

DBE/MBE The DBE goal for the construction contract is 15%.

SIGNIFICANT ISSUES:
This project has been coordinated with the City of Jacksonville Beach's project to align Penman Road South with Penman Road North at Beach Blvd.

PROJECT MANAGER: Larry Wehner

CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com

PLAN YOUR TRIP

Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, the Trolley or the JTA Skyway. Read more.


Have you used "Plan Your Trip" feature? Let us know your thoughts.


Click here to take our "Plan Your Trip" Survey.

QUICK LINKS
SEARCH