Status Report is for April 11, 2008

This is a rendered view of Branan Field Chaffee Road - 103rd St. to I-10.  For more information call 630-3181.

DESCRIPTION:
The FDOT is responsible for design, right-of-way, permitting and construction of this project, which consists of constructing a two-lane roadway from 103rd Street to New World Avenue (Cecil Commerce Center); a four-lane roadway from New World Avenue to I-10; and a new interchange at I-10. This section of Branan Field Chaffee Road will complete the link from Argyle Forest Blvd. to I-10.

STATUS:
Current Activity: DESIGN PHASE: Design contract awarded by FDOT to Parsons Transportation Group.

Funding: BJP Program allocation was $14 million. A transfer of $8 million from the Forest Street project and $3.8 million from SR 9A (I-295 to US1) revised the total allocation for this project to $25.8 million. A $32 million SIB loan is available in 2006.

Schedule: FDOT design completed. R/W is complete. Bids were received in late September 2006. Construction began in February 2007, with completion expected in the first quarter of 2010.

DBE/MBE
DBE participation will conform to FDOT policies.

SIGNIFICANT ISSUES:
FHWA required widening of I-10 to six lanes, from new interchange east to I-295, is currently under design. Construction scheduled for fiscal year 2008/2009.

PROJECT MANAGER: Florida Department of Transportation (FDOT)

CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com

PLAN YOUR TRIP

Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, the Trolley or the JTA Skyway. Read more.


Have you used "Plan Your Trip" feature? Let us know your thoughts.


Click here to take our "Plan Your Trip" Survey.

QUICK LINKS
SEARCH