Butler Blvd./I-95 Ramp Improvements

Better Jacksonville Plan, BJP-2
Status Report is for April 11, 2008

This is a rendered view of I-95/J.T. Butler Interchange project. For more information call 630-3181.

DESCRIPTION:
Add northbound and southbound I-95 entrance and exit ramps between Butler Boulevard and Bowden Road to reduce traffic congestion and improve safety. Click to following links to view project renderings:

STATUS:
Current Activity: DESIGN PHASE: Finalizing the design-build criteria package.

Funding: Revised BJP Program allocation is $14 million, as part of the I-95/Butler Interchange project.

Schedule: Complete Design-Build Criteria Package and Issue RFP in second quarter of 2008 (addition of Belfort Road turn-lanes, right-of-way acquisition and coordination of utility relocation have delayed schedule).

DBE/MBE
DBE participation will conform with City policies.

SIGNIFICANT ISSUES:
Drainage issues for new ramp lanes. Addition of Belfort Road turn-lanes. Permitting of project. Utility relocation coordination. Coordination of this improvement with planning work on US-1 to I-95 link, as a component of the JTB/I-95 ultimate configuration.

PROJECT MANAGER: John Davis, P.E., P.S.M.

CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com

PLAN YOUR TRIP

Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, the Trolley or the JTA Skyway. Read more.


Have you used "Plan Your Trip" feature? Let us know your thoughts.


Click here to take our "Plan Your Trip" Survey.

QUICK LINKS
SEARCH