Lenox/Normandy Blvd.
(Ellis Road to Normandy Blvd.)

Bond Funded
Status Report is for April 11, 2008

This is a rendered view of Lenox Ave./Normandy Blvd. project. For more information call 630-3181.

DESCRIPTION:
This project improves congestion relief and safety at the intersection by widening Lenox Ave. to three lanes from Ellis Road to Normandy Blvd. and upgrading the signal system. Additionally, drainage and flooding problems in the area have been addressed in cooperation with the City of Jacksonville. The CoJ segment of Lenox (Lane Avenue to Ellis Road) and the JTA segment of Lenox Avenue widening (from Ellis Road to Normandy Blvd.) have been combined into one construction contract, managed by the City, since the CoJ is the larger project.

STATUS:
Current Activity: CONSTRUCTION PHASE: The City of Jacksonville's contractor, United Brothers, began construction in early March 2007.

Funding: 1997 Bond Fund allocation is $2,004,796.

Schedule: Construction began in early March 2007. The roadway is complete. Signalization will finish in April 2008.

DBE/MBE
DBE participation will conform with City policy.

SIGNIFICANT ISSUES:

Approval of a Joint Project Agreement with the City.

PROJECT MANAGER: Hamid Tabassian

CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com

PLAN YOUR TRIP

Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, the Trolley or the JTA Skyway. Read more.


Have you used "Plan Your Trip" feature? Let us know your thoughts.


Click here to take our "Plan Your Trip" Survey.

QUICK LINKS
SEARCH