Soutel Phase 1
(I-295 to New Kings Road)
Bond Funded
Status Report is for April 11, 2008

DESCRIPTION:
Reconstruct an existing two-lane road to a four-lane divided
highway, and re-alignment of Pritchard Road and Soutel Drive
to connect at Old Kings Road. Project includes an overpass over
the Norfolk Southern Railroad, an at-grade crossing of the CSX
Railroad, and signalization work at the intersection of Old
Kings Road and New Kings Road. View
Project Map.
STATUS:
Current Activity: CONSTRUCTION PHASE: Construction
by Hubbard Construction Co. Pile driving has been completed
for the new overpass at Norfolk Southern Railroad, and construction
of the retaining walls is nearing completion. Drainage installation
and roadway construction are underway. Beam placement for the
new overpass at Norfolk Southern's railroad is complete. Click
here to link to the Public Meeting
Q & A.
Funding: 1997 Bond Fund allocation is $6,515,587,
plus a State SIS Grant of $4.6 million.
Schedule: Construction began April 30, 2007,
with completion scheduled for the second quarter of 2009.
DBE/MBE
DBE participation conforms with JTA policy.
SIGNIFICANT ISSUES:
None
PROJECT MANAGER: Richard Schwabe
CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com