A.C. Skinner Parkway Extension
(Belfort Road to Southside Blvd.)

Bond Funded
Status Report is for June 25, 2007

This is a rendered view of South East Access Road. For more information call 630-3181.

DESCRIPTION:
Widen A.C. Skinner Parkway existing two-lane road to four lanes at Belfort Road, and construct a new four-lane road from the end of the existing road to Southside Blvd.

STATUS:
Current Activity: CONSTRUCTION PHASE: Construction by John Carlo Co. began September 13, 2004, and was substantially completed and opened to four lanes of traffic on November 15, 2006. Project close-out and transfer to the CoJ is in process.

Funding: Funding allocation is $19.5 million.

Schedule: The easterly segment was completed by mid-June 2005, as scheduled. The entire project was substantially completed and opened to traffic on November 15, 2006.

DBE/MBE
DBE participation goal during construction is 15%.

SIGNIFICANT ISSUES:
None at this time.

PROJECT MANAGER: Robert Opland

CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com

PLAN YOUR TRIP

Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, the Trolley or the JTA Skyway. Read more.


Have you used "Plan Your Trip" feature? Let us know your thoughts.


Click here to take our "Plan Your Trip" Survey.

QUICK LINKS
SEARCH