Arlington Expressway Access Road
SAFETEA-LU Funded
Status Report is for April 11, 2008

DESCRIPTION:
This project involves transit shelter and pedestrian improvements
along Arlington Expressway's north frontage road east of University
Blvd.
STATUS:
Current Activity: DESIGN PHASE: Design began
in the first quarter of 2008.
Funding:Federal SAFETEA-LU allocation of $1.06
million.
Schedule: Design is scheduled for completion
in the third quarter of 2008.
DBE/MBE MBE participation will conform with
JTA policy.
SIGNIFICANT ISSUES: None.
PROJECT MANAGER: Neil Nance, P.E.
CONTACT:
Wendy Morrow, (904) 598-8733